Hanging Board at 9,000 Feet in February

Board does not care about the cold. Compound does. The truck does. Plan for those two.

OUTWEST1995

Five Colorado yards.
One outfit.

01

Get the building to temperature first

Compound needs the room above 50°F to cure, and it needs to stay there — not just while the finisher is in the room, but overnight. A heated room that drops to 30 at night is a room where the second coat cracks. Get the temporary heat in before the board, not after.

02

Do not leave compound on the truck

Ready-mix that freezes is not the same after. It separates, it goes lumpy, and it does not bond right. We keep it inside and load it last on cold mornings; it should come off the truck first and go inside. Do not leave a pallet on site overnight in January.

03

Let the board acclimate

Board that comes off a cold truck into a heated room sweats. Stack it flat, inside, and give it a day before it goes up. Hang it cold and the joints move as it warms.

04

Order earlier than you would in July

Our high yard sits at 6,601 feet and we deliver above 9,000 all winter. When the forecast turns, loads get staged at the nearest branch the night before rather than run the morning of. If Vail Pass closes, the load for a Vail job is already in Eagle. That works when we have the order ahead of the storm — so send it a day earlier than you think, and tell us the real must-have date.

05

Setting-type compound is your friend

Hot mud cures by chemical reaction, not by drying, so it sets on schedule in a cold room where ready-mix would sit wet for days. Use it for the taping coat and the fills, and save the ready-mix for the finish coat once the building is warm.

The branch makes the call